Cumulative spend, planned vs actual
Hover any point to see month-level detail. Solid line is actual, dashed is planned.
Hover the chart for monthly spend.
Interactive dashboard demo
A live, interactive dashboard for a 4-year multi-site research grant. KPI tiles, planned-vs-actual burn rate, category breakdown, and a filterable project portfolio. Hover anything for detail.
Sample data modeled on a typical NIH-style program: $4.20M over 48 months across 12 sub-awards at 6 sites.
Total awarded
$4.20M
Direct + indirect
Deployed to date
$2.69M
64% · on plan (-$0.04M)
Remaining
$1.51M
17 months left
Active projects
12
across 6 sites
Needing attention
4
2 at risk · 1 behind · 1 ahead
Hover any point to see month-level detail. Solid line is actual, dashed is planned.
Hover the chart for monthly spend.
Filled bar is deployed; full bar is total budget.
Hover any bar for deployed and remaining.
Click a status chip to filter. Click any project row for the budget breakdown.
| Project | Site | PI | Awarded | Deployed | % deployed | Status |
|---|
What this shows
The program is tracking on plan (64% deployed at 64% elapsed). Personnel and indirect costs are the dominant categories, consistent with an NIH-style budget. Of 12 sub-awards, 4 need attention: two have milestone slippage despite normal spend, one is materially behind on spend, and one is ahead of schedule. The dashboard is the single view a program officer needs to walk into a quarterly review.